CN-07- Security and Justice Construct New Three-Story Courthouse Building at Al- Faw District

CN-07- Security and Justice Construct New Three-Story Courthouse Building at Al- Faw District

  • LocationAl- Faw District
  • ClientBasra Province Government
  • Value4,475,450,000.00 IQD
  • CompletedMar.2017 - Mar.2020

Scope of works includes construction of new three-story courthouse building at Al-Faw district work included all civil, concrete, build, landscaping, MEP, parking as will supply and install two 1000 kg elevators, power generators, transformer and supply and install furniture. (Total Area 9,000 m2)
MEP Works includes;
– Supply and install two 1 MW power generators with fuel tanks.
– Supply and install 11KV/400 V, 2500 KVA transformer and connection with local power grid.
– Supply & install two 6 Persons (500 Kg) elevators.
– HVAC works, supply and install AC package units with all ducting works.
– Fire fight system (pumping, piping & sprinklers).
– Fire alarm system (Control panel, Smoke detectors, Heat detectors, break glass alarm buttons & Sirens).
– Plumbing works for water, storms and sewage systems.
– All electric power works (Cabling, Main circuit breaker, Distribution boards, Wiring, Power sockets, Trays, Conduits, Earthing system, Lighting and lightning system).
– Communication and IT system.
– CCTV system (8 MP Camaras, NVR, PoE Switch and Cat 6 wiring).